13 June 2025
Tower 2
- Excavation work has been fully completed.
- Column work from B1 to GF level is 64% completed.
- GF level slab and beam work is 25% completed.
- Next milestone: GF columns to 1st floor.
Excavation Work - 100% Completed
B1-GF lvl slab column - 64% Completed
GF lvl slab/beam - 25% Completed
Next Milestone - GF Columns to 1st floor